Factory building WEST 2 has been finished!

Construction of factory Building WEST 2 has been finished today!
It is the next milestone of the project of new production line. We are expecting the official start in March 2016.
Installation of technologies, cablings, following works and testing will start now and be in progress till autumn.
We are starting costruction of next factory building EAST at the same time. This building should be finnished till the end of November 2015.